At the end of April, the Rumanian tissue producer Petrocart has successfully started up their new Toscotec complete tissue productionline installed in Piatra Neamt, headquarter of the company since 1908.

Based on a turn-key concept and an average production of 75 tons per day, the new line includes the stock preparation plant for virgin and recycled fibers, a Modulo-Plus Tissue machine with single-layer headbox, double press configuration and TT SYD-12FT, the tissue machine auxiliary plants including a Milltech hood and steam & condensate system; A three unwind stands tissue slitter rewinder TT WIND-M completes the Toscotec scope of supply.

According to Petrocart green philosophy, the project was mainly focused on reduced energy consumption, usage of waste paper, recovery and re-usage of the water in the manufacturing process.

The project has been managed on the turn-key basis by Toscotec providing also the whole engineering services, erection supervision, start-up and training.

The Modulo-Plus Tissue machine.